OGK / E-ON 400 MW NG CCPP


Teknokon carried out the installation of the HRSG boilers, gas and steam turbine systems, BOP pipings and the auxiliary systems of 400 MW CCPP of OGK / E.ON Group in Shatura, Russia under the leadership of GE – Gama EPC consortium.

Client: GAMA - GE Consortium
Location: Shatura / Russia
Status: Completed
 

Detailed Scope of Works


Equipment Installation: CMI HRSG, GE 9FA gas turbine, GE D11 steam turbine, hydrogen cooled generator, stack, compressor station
Piping Erection: 10,000 WDI (Including P91, P22, P11 equipments)